 Former Daverick Motors Site, Lydiate - Planning Applications S/2009/1083 and S/2013/1076.

This was a contaminated site which was intended for housing and one plot at the centre of the site is still to be developed.  Under the Environmental Protection Act in 2010 pre-commencement of development contaminated land conditions had been placed on the development (under application S/2009/1083).  These conditions are imposed on contaminated sites to protect workers, existing and future residents and the general public from exposure to contamination. The first 3 contaminated land conditions are pre-commencement of development (including demolition and site clearance). 

These contaminated land conditions are phased and have to be satisfied in order prior to progressing to the next in the sequence (preparation and agreement of Phase I report – Preliminary Investigation (contaminated land condition 1), Phase II report – testing and analysis (contaminated land condition 2) and Phase III report – submission of a Remediation Strategy (contaminated land condition 3).

When these 3 contaminated land conditions are discharged, remediation only (safe removal of contamination from site) can take place. 

Page 73 of Sefton Council's Contaminated Land Inspection Strategy states (click here to view) "the Council recognises the importance of making decisions about contaminated land matters that are accepted by the community and are both defensible and transparent".  We are saying Sefton Council officers are not following this strategy or any legal requirements imposed on Sefton Council Officers, the Developers and the site itself.

In January 2013 when our account begins the developers had still not submitted a revised Phase I report to discharge the first contaminated land condition.  A Phase I report had accompanied the planning application in 2009 but this had been rejected by Sefton Council officers because it didn’t correspond with Sefton Council’s evaluation of the site (click here to see internal memo dated December 2009).

A revised Phase II report dated February 2014 identified asbestos as well as concentrations of arsenic, lead, mercury, benzo(a)pyrene, ideno(123-cd)pyrene and dibenzo(ah)anthracene  as exceeding  their respective GAC/SGV and therefore a potential human health risk.  

Diagram of Contaminants Found On Site

We are saying the findings of this report show what contamination existed on site as at February 2014 but are not an accurate account of what contamination was originally on site.  Photographs at various dates in 2013 and early 2014, before testing and analysis took place, show groundwork being unlawfully undertaken.  Contaminated soil was moved around the site and taken off  the site and soil brought on to site to doctor it. 

Before pre-commencement of development contaminated land conditions were discharged on 2nd September 2014 which would only allow remedial work to take place on the former Daverick Motors site, Sefton Council and HSE had already allowed  the following unlawful activities (how could the developers comply with the instructions given in this decision notice when they had already breached all the contaminated land conditions) See Decision Notice of 2nd of September 2014:- 

Unlawful demolition - buildings bulldozed down by a hydraulic machine with grabbers, spreading contaminated dust/building debris everywhere

1640  kgs  (over 1½ tonnes) of asbestos was allowed to be  unlawfully removed from site,

Contaminated building debris moved around the site, 

Contaminated soil removed from site unlawfully and soil imported on to site to doctor it. 

48 loads of hazardous waste unlawfully removed from site and taken to unknown destinations (see copy consignment notes in our possession dated 22nd May to 3rd July 2014). NOTE: consignment note 12165 dated the 22nd of May 2014 covering 8 loads states at the bottom of the note "no asbestos".  These 8 Loads were in fact taken from the asbestos slop located at testing point WS2.



A house built and the foundations laid for a second house. 

The first photograph taken in April 2014 shows a concrete delivery for the foundations for the first house and proved that the foundations for this first house had already been excavated with the contamination still in the ground, exposing workers undertaking this unlawful work to contamination as well as a community.  Part IIA of the Environmental Protection Act stipulates that contamination must be removed before any development takes place. Who checked the foundations and approved their construction? 

How could Sefton Council sign off contaminated land conditions to permit remediation to commence when they had allowed unlawful remediation to take place and for houses to be constructed in contravention of Part IIA of the Environmental Protection Act?   Every time soil was excavated over a number of years, the general public was put at risk of contamination.  Sefton Council had already allowed unlawful demolition and then covered up with retrospective demolition documentation and were now issuing retrospective documentation once again, this time for Part IIA contaminated land conditions.

On 29th January 2013 buildings which residents knew contained asbestos and other harmful contaminants (having read a report which accompanied the Planning application in 2009) were being bulldozed down by a hydraulic machine with grabbers and contaminated dust and building debris was going everywhere.   To avoid drawing attention to what was going on the developers had deliberately not displayed asbestos and demolition signs.   Residents complained to both Sefton Council and HSE about exposure to contamination (see complaint to HSE).

No-one should have been working on this contaminated site and Sefton Council and HSE officers were well aware that the developers had not complied with any pre-commencement legal requirements imposed on them. 

Upon receiving our complaint, HSE would have discovered the developers had not submitted a Form F10 (Notice of a Construction Project) under the Construction Design and Management Regulations (CDM) which is a legal requirement prior to demolition being undertaken.  This F10 Form was not submitted until May 2014 (we have a copy in our possession).

If demolition were to be allowed, this is the demolition procedure which must be followed before buildings are demolished.  (In this case demolition could not be allowed because the pre-commencement of development contaminated land conditions had not been discharged.) Under Section 80 of the Building Act 1984, the developers must give notice of intended demolition to the council, together with documentation to determine what contamination exists within and on the buildings and how the contamination is to be disposed of (submission of a contamination/asbestos survey and a method statement).  A UKAS Clearance Certificate  is then required to prove that the buildings are clear of contamination and safe to demolish.  The council has up to 6 weeks to assess the situation and, if they are satisfied that demolition can be undertaken safely, issue their counter-demolition notice of intended demolition under Section 81.  Under the Act residents and statutory bodies must also be notified.

On 29th January 2013 no notice of intended demolition and accompanying documentation had been produced by the developers for Sefton Council.  Both Part IIA and demolition procedures involve risk assessments and testing and analysis before any work is allowed.  None of these legal requirements had taken place.

This was an emergency.  Residents were being exposed to contamination, including asbestos.  They had complained to both Sefton Council and HSE officers and had expected them to take the appropriate action to protect the community.

Developers were working on site unlawfully, smashing down buildings containing asbestos and other contaminants.  Unknown to residents, the owner of the demolition company had been investigated in 2005 by the Environment Agency and the BBC, following complaints from nearby residents who had observed over a period of time his company using tractors to dump 44,000 cu metres of hazardous waste containing white, brown and blue asbestos on a nature reserve in Scarisbrick, Lancashire (http://news.bbc.co.uk/1/hi/magazine/4457663.stm).

In 2005 this hazardous material would have originated from a number of contaminated sites similar to the Daverick Motors site and should have been disposed of safely at considerable cost to landfill.  This man was operating a very lucrative business by selling on contaminated soil for landscaping purposes.  In 2005 he should have been prevented from operating with hazardous material ever again.

Now in 2013 residents living near the Daverick Motors site had caught him again undertaking unlawful demolition on a contaminated site without following any legal procedures as above but these residents were unaware of his past history

HSE purposely did not react to our serious complaint, allowing the developers to start, progress and complete unlawful demolition.  We have since discovered this is the way HSE behave when residents make serious complaints about exposure to contamination, having experience now of dealings with HSE on other contaminated sites.

HSE would have known that an asbestos survey and method statement had not been submitted to Sefton Council for the council to determine that demolition could be undertaken safely.  They would also have known that they had not received a HSE F10 form (notification of a construction project) which is a legal requirement when demolition is involved. 

Sefton Council officer logs obtained in 2016 reveal that after receiving our complaint, a contaminated land officer contacted a team leader in another department (Environmental Protection) to deal with the complaint.  He advised them that the site had permission for a residential development and that a desk study report they had reviewed in 2009 identified asbestos in the insulation and roofing materials.  He must have known no work should have been taking place because this was the report to discharge the first contaminated land condition which his team had rejected.  He also commented that he could not find a record of an asbestos survey on the council’s systems (Flare and the planning portal.)   (The developers had failed to comply with any legal requirements so there could not possibly be any documents) click here to see links to logs.

The Environmental Protection team leader then gave the following instructions to her colleagues:-  “Could anyone bob out to this site today to check if they have all the correct paperwork for the demolition if there is asbestos present on site and that procedures are in place etc.  If you can’t make it I’ll see if I can go tomorrow.  Can you let me know if you can make it today.”

One officer went out and was on to site for only 3 minutes as evidenced by a CCTV camera.  The logs show that the officer spoke to a sub-contractor who advised that as far as he knows all the asbestos material had already been removed prior to his company getting there to dismantle the building.  The officer also commented that no asbestos material was visible on site.

What is this all about when the contaminated land officer had already given his colleagues sufficient information to stop the site by advising there was no documentation in Sefton Council’s possession?

There was obviously no intention of stopping this unlawful demolition.  Sefton Council officers were not only covering up for the developers they were also covering up for themselves and what they had allowed to take place.

Unlawful demolition continued for a further 3 days until all the buildings were down.

On 1st February 2013, after they had allowed the buildings to be completely unlawfully demolished and when they were fully aware that there was no legal documentation in place such as an asbestos survey and method statement, Sefton Council’s building control department issued their counter demolition notice of intended demolition to the developers only withholding notice (which is a legal requirement) from affected residents.  Residents did not discover the existence of this intended demolition document until November 2014 (*see later in account). Click to view Counter Demolition Notice.

How can a council allow an individual who has a history of dumping hazard waste to operate unlawfully on a contaminated site in the first place and, when residents complain about exposure to contamination, give him a green light to continue his unlawful operations?

We now have a copy consignment note dated 6th February 2013 showing 1640 Kgs (over 1½ tonnes) of asbestos removed from the Daverick Motors site and taken to Skelmersdale  landfill.  How do Sefton Council officers account for such a large quantity of asbestos removed from site when on 29th January the officer who attended site said there was no asbestos visible and took the word of an operative working unlawfully on site that asbestos had already been removed?  How was this asbestos identified when no testing or analysis had taken place (no asbestos survey had been produced)? Click to view consignment note.

When residents had not received any feedback to their complaint from either Sefton  Council or HSE officers, the main garage building had been demolished and groundwork was continuing on site, residents involved their councillor who was assured by Sefton Council officers that there were no planning or building control issues.  This was completely untrue.  There were very serious contamination issues and breaches of statutory legislation by the developers and Sefton Council involving Sefton Council’s planning, environmental protection and building control departments (again refer to logs 29th Jan to 5th March).

A Councillor was involved and was asking questions on behalf of residents.  Involvement of a third party i.e. HSE could assist in deceiving residents and their Councillor into believing everything was in order.  Sefton Council officer logs reveal that a Sefton Council officer telephoned HSE on 15th February 2013 to ask if HSE were in receipt of any information concerning safe removal of asbestos. (Note: These documents should have been in Sefton Council’s possession prior to demolition i.e. prior to 29th January 2013 for the Council to assess that demolition could be undertaken safely, together with the developers’ notice of intended demolition.) 

Sefton Council officers were advised to complete an enquiry form online.  HSE then emailed Sefton Council on 5th March advising that unfortunately HSE could not send Sefton Council the documents but that HSE had requested and were in receipt of a pre-demolition survey, method statement, building control’s acknowledgement of demolition letter and a hazardous waste consignment notice dated 6th February 2013.  Sefton Council and HSE officers were using these documents to cover up for the unlawful demolition.

This email was forwarded to the councillor to show to affected residents who believed what they were being told by HSE and that everything was in order.  They did not pursue the matter any further.

The cover-up continued with fabricated planning documents and reports stating “seeks demolition” and “following demolition” implying that demolition was yet to happen when it had already occurred.

It was not until the end of November 2014 that residents discovered the existence of a four page counter-demolition notice of intended demolition dated 1st February 2013 and  issued to the developers only (see above in the account).  

Affected residents and statutory bodies were named in the Council’s notice of intended demolition.  FOI requests have failed to produce statutory body copies and residents have never received or seen this document.  It was impossible now to circulate this intended demolition document for affected residents and statutory bodies to have an input into safety after the buildings had been allowed to be unlawfully demolished.  For this reason circulation was withheld from both statutory bodies and affected residents.

Residents realised that they had been deceived.  These documents had been issued after the buildings had already been demolished and Sefton Council and HSE had allowed developers to contaminate residents for a further 3 days after their complaint but residents still did not realise the full extent of that deception and that residents had been exposed to contamination over a number of years until they received FOI information from Sefton Council in 2016.  Sefton Council had allowed unlawful work to continue on a contaminated site at the expense of  the health and safety of nearby residents and also the general public.

On 2nd December 2014 we made a formal complaint to the Chief Executive of Sefton Council, supported by a petition from nearby residents.  We were complaining about exposure to asbestos and other harmful contaminants and Sefton Council’s failure to circulate their letter of intended demolition to affected residents and statutory bodies.  Residents were still unaware that this contaminated site came under Part IIA of the Environmental Protection Act.

On 9th December 2014 the Director of Built Environment at Sefton Council at that time replied to our formal complaint.  We now know this letter is a complete fabrication of what happened on 29th January 2013 and subsequently.  We attach copy of this letter and also copy of the Sefton Council officer logs for 29th January  2013 and after.  The accounts differ significantly (see the anomalies between the letter and logs).   Why would a Chief Executive of a council deceive residents over their health and safety? 

The developers and Sefton Council had not complied with the legal requirements imposed on them and on this contaminated site.  What was taking place was unlawful and residents were being contaminated.  Once again residents were being deceived.  There is no mention of Part IIA contaminated land conditions.  The letter implies that HSE were contacted immediately.  We know from Sefton Council officer logs that Sefton Council did not contact HSE until 15th February 2013 and again on 5th March 2013 requesting documents which should have been in Sefton Council’s possession for them to assess that safe demolition could be undertaken (see earlier in our account).

In June 2014 a Sefton Council Planning Monitoring Officer visited the site and expressed concerns that the buildings had gone and a house had been built when a remediation strategy had not been agreed but this Sefton Council officer did not stop unlawful work on site (see Sefton Council officer logs).

In July 2014 a HSE inspector visited the site when house construction was underway. This is the same HSE inspector involved with many of the other sites in this blog.   Why was a HSE inspector now out on site?  This was some 18 months after HSE had failed to react to residents' complaints about exposure to contamination on 29th January 2013 and when HSE knew there was no documentation in place under the HSE Construction Design and Management Regulations (CDM).

The inspector issued a contravention notice for various health and safety contraventions:-

Failure to provide suitable and sufficient welfare facilities

Failure to plan, manage and monitor the construction phase of the project including

insufficient escape routes from the scaffolding::  fire protection and detection measures not built into the structure along the way:  perimeter of the site not complete where it backed on to the adjoining property resulting in an insecure site

As the building in progress is of timber frame construction, the above failures should be addressed as a priority as operatives on site and members of the public are potentially at risk from the spread of fire on and off the site.

The competent person in charge of the site does not hold the appropriate qualifications. (see Inspector’s Report dated 9th July 2014).

HSE had allowed unlawful work to take place on this contaminated site for over 18 months ie since 29th of January 2013 when residents first complained to them and they did not attend the site.  Now a HSE inspector who had a legal duty to protect workers on site and a community from exposure to contamination was allowing unlawful work to continue on this contaminated site further exposing workers on site, residents and the general public to contamination.  The Inspector completely ignored the fact that no work at all should have been taking place because the pre-commencement of development contaminated land conditions had still not been discharged and any development (including excavation for house foundations and removal of hazardous waste from site) was unlawful.  On the day of the Inspector's visit four loads of hazardous waste were being unlawfully removed from site.  Unlawful house building and unlawful removal of hazardous waste were taking place at the same time and a community and workers on site were being exposed to contamination.  Sefton Council and HSE Officers were allowing an individual with the history of dumping hazardous waste and developers who were not complying with their legal requirements to continue operating unlawfully on a contaminated site to the detriment of the health and safety of workers on site and a community.  

Photographs taken in 2016 and 2017 show asbestos taped up and bundled and moved to various locations on the site.  This was uncovered when excavating for foundations for the northern part of the site  ie plots 6,7,8 and 9. Why is contamination still being found onsite ie asbestos when houses have already been constructed?


This site is surrounded by housing with 2 Primary Schools nearby.  A lollipop lady is positioned adjacent to the corner of the site to cross children and their parents over this busy main road.  There is a bus stop and bus lay-by opposite the site.  All these people have been exposed to contamination with unlawful work being allowed to take place over a number of years by Sefton Council and HSE Officers.

Our experience with this site is not an isolated incident.  One resident gathering evidence for the former Mayflower industrial site which is currently being developed has died recently from cancer and another resident whose house backed on to this site has contracted cancer.

This prompted us to undertake a preliminary survey of our own area surrounding the former Daverick Motors site with alarming results of clusters of cancer and respiratory problems which you would not expect in a rural area and the effects of exposure to asbestos have yet to take their toll.  The young children could, in their late teens or early adult life, develop mesothelioma or lung problems due to asbestos exposure.  Residents and the general public have been contaminated and treated like third world citizens in the whole process.   The number of people who have been potentially contaminated is immense.  All these people have been exposed to contamination with unlawful work being allowed to take place over a number of years by Sefton Council and HSE Officers. See survey of cancer and respiratory illnesses within the adjacent community.  

A wider public could be affected with hazardous waste unlawfully removed from site by the same individual who was responsible for the unlawful demolition.  These corrupt practices have been continuing from 2005 and earlier and will continue until those involved are brought to justice.

What we have uncovered should not be happening in the 21st century.  We expect our national government and the press to expose these environmental crimes to protect the public.  It is their duty to do so when presented with compelling evidence.

Developers, Sefton Council and HSE will be held responsible for the deaths of residents and the general public who have been exposed unnecessarily to contamination.  Laws are imposed on contaminated sites to protect the public.  Public bodies have a duty to enforce these laws and not cover-up what has actually happened.

By ignoring these environmental crimes and allowing them to continue, more and more people will lose their lives.

No comments: