 Pre-commencement of development contaminated land conditions had been imposed on the development in January 2017 under Part IIA of the Environmental Protection Act.  These conditions had to be discharged before any development/site clearance could take place on this contaminated site.  Under Section 55 of the Town and Country Planning Act “demolition” is classed as “development”. See approval notice here.

This structured legal procedure is put in place to protect residents, the general public and workers on site from exposure to contamination and ensure that developers do not undertake unlawful work on site to cut costs as happened here.

The contaminated land conditions are phased and each condition must be satisfied in order prior to progressing to the next in the sequence.  Contaminated land condition 1 involves a preliminary assessment (Phase I Report) of potential contaminants relating to the site’s present and past uses which must be approved and discharged by the local authority.  Testing and analysis – contaminated land condition 2  (Phase II Report) then follow to confirm the findings of the Phase I Report.  The 2nd contaminated land condition is then discharged with local authority approval of the Phase II Report.  On the findings of the Phase I and Phase II Reports a remediation strategy – contaminated land condition 3 (Phase III Report) is then prepared for discharge by the local authority.  Only then when all 3 contaminated land conditions have been discharged can remediation of the site/removal of contaminants take place.

Under pressure from residents and their councillors who were fearful for residents’ safety and were continually asking Sefton Council and HSE officers to stop the site and make safe, Sefton Council officers then validated an application from the developers to discharge all 3 contaminated land conditions simultaneously when each condition must be satisfied separately and in a particular order in accordance with Part IIA of the Environmental Protection Act.  This application was subsequently approved by Sefton Council officers under delegated powers on 5th April 2018.  See application to discharge all 3 contaminated land conditions and approval notice.

Before any of the contaminated land conditions had been discharged on 5th April 2018 (which would permit remediation only to take place), the developers of the Mayflower site were allowed by Sefton Council and HSE officers to undertake demolition, site clearance, excavation and groundwork for drains and demolition debris was also crushed on site in contravention of Part IIA of the Environmental Protection Act and exposing residents to further contamination.  Sefton Council and HSE officers had knowingly allowed developers to contravene legislation imposed on this development to protect the general public from exposure to contamination.

Residents’ safety had been compromised.  Sefton Council officers were well aware of all the unlawful practices that had taken place but were not prepared to comply with the law by stopping the site.  They were more intent on issuing retrospective documentation which would allow unlawful work to progress further exposing residents to contamination.

Sefton Council officers withheld this site’s status as a contaminated site under Part IIA of the Environmental Protection Act from affected residents and also withheld notice of intended demolition under Section 81 of the Building Act when it is a legal requirement for a local authority to inform affected residents because their safety is involved.

 

The following is an account of the unlawful practices which Sefton Council and HSE allowed to take place on this contaminated site.  The pre-commencement of development contaminated land conditions had not been discharged and any work taking place on site was unlawful.

February 2017 – unlawful work started on site with the removal of trees (site clearance). 



March 2017  - buildings containing asbestos and other contaminants were being unlawfully demolished and surrounding residents were being contaminated by dust debris from this unlawful demolition.  To avoid attention, the developers had deliberately avoided displaying demolition or asbestos signs as required by law.  Residents complained to both Sefton Council and HSE  believing these authorities would protect them against unnecessary exposure to contamination.   




Between March and August 2017 - before the contaminated land conditions were discharged and a safe remediation strategy agreed, concrete bases, concrete rafts, roads and drainage were removed, water services and electricity disconnected.  Groundwork, including digging out for drainage, took place and contaminated soil was moved all around the site and stockpiled on site.   A machine was brought on to site to crush the demolition debris from the demolished buildings, further contaminating residents.   


On 4th July 2017 an asbestos survey for the Garage only was prepared for the demolition contractors.   This was not a full refurbishment/demolition survey which must be submitted to the council before demolition is even contemplated.  The surveyors recommended that if the report were to be used for demolition purposes, they revisit the site and investigate further. 

Amosite (brown asbestos) was identified at several locations as well as Chrysotile (white asbestos).  Crocidolite (blue asbestos) was identified in the external roof to the garage. Not all areas were surveyed namely behind sampled materials, within live services, areas above 5m in height, limited access within timber box-work to metal flue in area 2, above ceiling voids where no safe walk access could be gained, ceiling void areas were full of scrap material and timber, no access to high level roof, live services throughout, unsafe ceiling access throughout.  

There were a number of other buildings on site which required full refurbishment/demolition surveys to be undertaken and all contamination to be removed safely and legally and UKAS clearance certificates issued prior to the buildings being demolished.

August 2017 -  in a Phase II Ground Investigation Report contaminants with elevated concentrations in soils were recorded as follows:- Lead, Nickel, Arsenic,  Benzo (b)fluoranthene,  Benzo(a)pyrene,  Dibenzo(ah)anthracene and Asbestos (Chrysotile (white) and Amosite (brown) and therefore a risk to human health.  See Phase II report.

September 2017 - residents were involved with HSE and Sefton Council with concerns over health and safety.

October 2017 photographs were submitted to Sefton Council’s Environmental Protection Department showing severe dust contamination lying on outdoor furniture in a property at Abbots Close which backs on to the site.  Cars in Abbots Way, further from the site, were also covered in dust contamination.  The crushed debris was heaped on the site some 20ft high at this time.    


A Sefton Council officer came out to Abbots Close and took photographs himself of substantial amounts of brick and building debris lying on a table.  He recommended reduction of the mound and covering it.    The officer should have stopped unlawful work on site to protect residents from further contamination.  The mound was not reduced until December 2017 and was not covered.  The building debris remained on site still uncovered and residents were being subjected to contaminated dust being blown over from the site. 

CIRIA (Construction Industry Research and Information Association) advises that building rubble may contain free fibres of asbestos and fragments in rubble can be difficult to detect by the naked eye (Asbestos in soil and made ground: a guide to understanding and managing risks. Ready reference (SP168). 

By November 2017 buildings associated with the late 19th Century Reciprocity Brewery had been demolished.   A condition had been placed on the Planning approval (condition 3), in the interests of built heritage, requiring the implementation of a programme of archaeological building recording in accordance with a written scheme of investigation be submitted by the applicant and approved in writing by the local planning authority before any development took place.  There is no record of this recording having taken place before the buildings were demolished. 

These buildings had been demolished without the developers undertaking an asbestos/contamination demolition survey. 

December 2017 onwards the drains were dug out and the foundations of the care facility on site were marked out.   There were mounds of contaminated soil on site, contaminated soil was being moved around the site..  Every time soil was being lifted and moved around site, workers and the public were being contaminated.  Contaminated dust was being blown over into properties in Abbots Close, backing on to the site and further afield into properties at Abbots Way. 


The developers and Sefton Council officers knew exactly what contaminants had been identified in August 2017 :- Lead, Nickel, Arsenic,  Benzo (b)fluoranthene,  Benzo(a)pyrene,  Dibenzo(ah)anthracene and Asbestos (Chrysotile (white) and Amosite (brown) and therefore a risk to human health yet unlawful work was allowed to progress on site.  None of the contaminated land conditions had been discharged and no remediation had taken place. 

Discharge of contaminated land conditions

23rd October 2017 - the developers submitted an application to discharge all 3 pre-commencement of development contaminated land conditions simultaneously when each contaminated land condition must be satisfied in order prior to progressing to the next in the sequence.  Sefton Council officers should not have accepted this application when they were well aware that unlawful work had started, progressed and was continuing on this site since January 2017 contravening Part IIA of the Environmental Protection Act.  There had been a number of complaints from residents during this time because residents were being exposed to contamination.  Sefton Council officers should have been reacting to residents’ complaints and prosecuting those involved in these environmental crimes instead of forcing through retrospective documentation to give developers full planning rights to develop the site.  We are saying that Sefton Council officers had now become complicit in environmental crimes. 

10th November 2017  - one of the ward councillors emailed the Sefton Council case officer requesting a “call-in” of this application so that it might be discussed by a planning committee “due to various issues which have been raised and need addressing in full before any conditions can be removed.”  The ward councillor had already emailed various questions relating to the pre-commencement of development contaminated land conditions and was unhappy about the case officer’s response.  See email of 10th November.

21st November 2017 – 11 days later the case officer replied asking the ward councillor for specific reasons why she wished to have the application heard by a planning committee (“called-in”).  There was obviously no intention of stopping unlawful work on this contaminated site.  Residents were being exposed to contamination  and their complaints were being ignored by Sefton Council and HSE officers.  Residents and their ward councillor wanted to make planning committee members aware of what was happening on this contaminated site.  Sefton Council officers were denying residents their democratic rights and residents’ safety was being compromised.  See email of 21st November.

We quote from page 73 of Sefton Council’s Contaminated Land Strategy and the council’s commitment to community involvement which Sefton Council officers were now failing to follow:-

“Land affected by contamination may be of relevance to members of the community other than owners and occupiers.  The use and condition of land may impact on the wider community especially if the contamination poses a risk to human health.  For those affected by contamination, the Council will endeavour to:

Inform the affected parties of potential risk arising from contamination

Consult on proposed actions in relation to contaminated land

Keep affected parties informed of decisions taken

The Council recognises the importance of making decisions about contaminated land matters that are accepted by the community and are both defensible and transparent.

If practicable, and indeed necessary the findings of any inspection will be communicated to the affected community and consultations undertaken on the best way to achieve the successful remediation of the contaminated land problem.

As noted above, public acceptance of any decisions made is very important if contaminated sites are to be managed effectively.  Effective risk communication is thus an essential element in the implementation of this strategy.”

21st November 2017 – the ward councillor replied to Sefton Council’s case officer as follows:-  The main concern is protection of residents’ health and safety.  It is quite clear that planning have not ensured that all procedures are followed correctly before demolition takes place.  Can you explain why?   Laws are in place to protect the public from unnecessary exposure to contamination.  I would not expect any conditions to be discharged until a full investigation has taken place and we can assure the residents that there are no problems with regard to how the demolition was carried out and that we are able to show them all the relevant documents to prove this.  I do feel that this particular site and demolition process and the failure to follow the law and procedures should be brought before the full planning committee.

The residents have many photographs of what has taken place on the site, together with video recordings and it is very clear that no precautions were taken when the site was demolished.  This can have very serious consequences in the future as you will know that only one speck of dust from asbestos can cause problems in the future years.  We have a duty to protect existing residents and this has clearly not happened on this site.  Some residents had so much dust in their gardens that they were able to take a sample which I believe is being sent off for analysis.  It should not be up to residents to try and protect themselves against unlawful demolition and the consequences from this on contaminated land or indeed from buildings that have asbestos in them.  There is a clear duty of care here and as a council we should ensure that all our residents are safe.  There is a primary school situated close to this site and depending on which way the wind was blowing when the demolition took place we could have a major issue. See ward councillor email 21st November. 

Listen to Radio Merseyside Mayflower Industrail Estate:

22nd November 2017 – the ward councillor emailed the case officer again asking for confirmation that various statements are correct and asking questions concerning unlawful work on this contaminated site and the pre-commencement of development contaminated land conditions.   See email of 22nd November.

29th November 2017 – the ward councillor emailed the case officer again because she had not received a reply to her email of 22nd November.  She had asked for documents which she had not received and asked for them again as a matter of urgency.   See email.

29th November 2017 – the case officer replied to the ward councillor.  He was deliberately misleading her with his answers.  At this point we are asking why had he been ignoring a request to supply documentation and why was he ignoring the fact that residents were being contaminated?  There were two issues here – pre-commencement of development contaminated land conditions under Part IIA of the Environmental Protection Act and demolition procedures under the Building Act 1984.  The contaminated land conditions  prevented any development (including demolition) being undertaken until those conditions had been discharged and a full refurbishment/demolition survey had not been undertaken.  Demolition could not even be contemplated until all contamination had been identified and removed lawfully from the buildings.  See email here.

30th November 2017 – Sefton Council’s building control department emailed the ward councillor enclosing intended demolition notice dated 7th February 2017 and Sefton Council’s counter demolition notice dated 2nd March 2017.  Where is the demolition asbestos survey and a UKAS clearance certificate to prove the buildings are safe to demolish?  However, as stated previously pre-commencement of development contaminated land conditions prevented any demolition taking place on this contaminated site. See email here.

6th March 2018 – The ward councillor emailed the case officer asking for an update.  The pre-commencement of development contaminated land conditions had not been discharged and the application had not been brought before a planning committee.  Meanwhile unlawful work was continuing on site.  See email here.

4th April 2018 – a month later a team leader replied to the ward councillor.  He advised there had been a long delay in the determination of the application due to the requirement of additional information that was requested from the council’s archaeological advisor.  He confirmed that the information has now been received and acceptable information has been submitted to the authority to grant approval of the application.  He appreciated that the ward councillor had requested the application to be called-in for consideration by members of the planning committee.  However, the constitution (which was amended on 25th January 2018) allows the ability for such applications (which are in essence a technical assessment of details following the substantive decision) be delegated to the Chief Planning Officer.  For such reason, I can confirm the application has now been approved.  We are saying approval of pre-commencement of development contaminated land conditions imposed under Part II A of the Environmental Protection Act are not technical matters but acknowledgment of compliance with legislation.  The laws of our land cannot be over ridden by a local council's constitution.   See email here.

The ward councillor had first made her request on 10th November 2017 prior to the amendment being made.  Residents’ safety had been compromised and now the council was unlawfully removing residents’ legal rights and councillors' democratic rights.   Residents and their councillor had been sent round in circles allowing developers to continue unlawful work on site and meanwhile Sefton Council officers were amending the council’s constitution to prevent the ward councillor calling-in the application.  Sefton Council officers had forced through a so-called democratic vote by elected members to remove residents’ democratic rights to safety.

 

Unlawful demolition of buildings on site

Demolition procedures come under the Building Act 1984 and require prior notice to be given to the Council, statutory bodies and affected residents.  Developers are also required to submit documentation (such as a method statement for the demolition and in this case a pre-demolition asbestos survey) to the Council in support of their demolition application.

On 3rd February 2017 a Risk Assessment and Outlined Method Statement for the safe demolitions and site clearance at the Mayflower site was prepared by a demolition company and submitted to Sefton Council.   Page 6 of this Method Statement under Section 5 “Tasks covered within this method statement” acknowledges the existence of licensed asbestos contaminated materials on site.  How can you have a method statement when a refurbishment/demolition asbestos survey has not been undertaken and the full extent of contamination in and on the buildings and on the site itself has yet to be determined?   The full extent of contamination was not determined until August 2017 with the submission of a revised Phase II Ground Investigation Report.  

A Phase I Preliminary Investigation (1st contaminated land condition) had accompanied the original Planning Application but this was considered to be insufficient by Sefton Council’s contaminated land officer and a number of concerns highlighted that needed to be addressed.  One concern was the proposal to undertake site investigation while the site was still operational which obviously restricted access for site investigation works.

7th February 2017-  the developers submitted a notice of intended demolition to Sefton Council naming the demolition contractor  and the intended date of demolition as 1st March 2017.  No notice was given to effected residents.  See notice of intended demolition.

2nd March 2017 - Sefton Council issued a counter-demolition notice of intended demolition.  This sets out rigorous procedures to be followed under Section 81 of the Building Act where demolition is concerned and also removal of asbestos from buildings prior to demolition under The Control of Asbestos Regulations. We quote from the document “Asbestos has been used in all sorts of places and you cannot assume the buildings are free of it.”  And “Prior to demolition you have a legal obligation to ensure that all the buildings involved are free from asbestos containing materials.”  A refurbishment/demolition asbestos survey had not been undertaken.  See counter-demolition notice of intended demolition.

This document was supposedly copied to affected residents in Abbots Close, Lovelady Grove, Royal Crescent, Alt Road, Gable Mews and Liverpool Road, Formby.   Checks have revealed that residents most certainly did not receive copies.

Why did Sefton Council issue a counter-demolition notice without a refurbishment/demolition asbestos survey and when there were historic surveys still to be undertaken and contaminated land conditions had not been discharged? 

Where is the UKAS clearance certificate to say that the buildings are clear of asbestos before being demolished?

 

No comments:

Post a Comment

Illegal Waste Site Formby

 Retrospective Planning Applications DC/2020/0098 and DC/2020/02197 This site (in the green belt and on a flood plain) had been heavily pr...